Louisiana
| Passed Legislation |
| Bill Number |
Date Introduced |
Sponsor |
Description |
Signed into Law |
| HB 354 |
4/13/2009 |
Jackson G |
Relates to public contracts; extends the time relative to the utilization of design-build contracts under certain circumstances; authorizes other public entities to utilize the design-build method under certain circumstances. |
07/10/2009 Act No. 523 |
| SB 351 |
6/2/2009 |
McPherson |
Provides for authority of the Department of Transportation Development (DOTD) to execute design-build contracts; provides for review. |
05/07/2009 Chapter No. 2009-36 |
| HB 833 |
4/17/2009 |
Dove |
Allows for the contracting authority of any State Department or Agency to include construction management-at-risk, operation and maintenance, design-build, design-build-operate and maintain, and design-build-finance-operate and maintain. |
7/7/2009 |
Transportation-Specific Procurement Legislation
| Existing Statute |
| Transportation Agencies with Authority |
Citation |
DOT Procurement Process |
| Authorization for DOT to select projects or combine a program of projects utilizing design-build;
DOT may also use design-build in areas impacted by a hurricane, including areas adversely impacted by increased population and traffic as a result of a hurricane;
Military Dept. may use design-build on any infrastructure construction project in areas affected by Hurricane Katrina or Rita through 6/30/2010 |
LA. REV. STAT. ANN. §§ 48:250.2 –4, 48:442.1;
LA. REV. STAT. ANN § 29:42 |
Two-phase selection process; DOT will identify the specific requirements for the second phase depending on the complexity of the project; the selection method uses an adjusted score determined by three components: (1) technical score; (2) time value; and (3) the price proposal; DOT must submit any project selected for design-build to the House and Senate Transportation, Highways and Public Works Committees for approval. |
|