Benjamin P. Grogan and Jerry L. Dove Federal Building

Benjamin P. Grogan and Jerry L. Dove Federal Building
Miramar, Florida
Challenge Design-Build Project Delivery Addressed:
The GSA sought a facility that meets their P-100 guidelines, performance specifications and the FBI’s Program of Requirements (POR) and achieve occupancy by December 2014. Despite a request to complete various changes and additions for the electrical and communication components, which was estimated to add four months to the project, design-build allowed Hensel Phelps to work closely with the owner and furniture vendor to facilitate the manufacturing of the systems and shorten lead times. This achievement allowed the team to meet the original final completion date.
 
Summary:
This was a bridging design-build project consisting of four buildings in a campus environment located near the Everglades. This project was designed and built to be LEED Platinum Core and Shell (C&S) certified, LEED Gold Commercial Interiors (CI) certified and Sustainable Sites Initiative (SSI) Two Star certified. Totaling 383,000 square feet, the project includes enhanced security specifications, an enclosed parking structure and multiple buildings on the 20-acre site. The GSA required a facility that met the Level 4 Interagency Security Committee criteria. The 303,552 square feet combined, six- and seven-story office towers are connected by a six-story link and include executive office spaces, private offices, team office spaces, conference space, storage, a fitness center, computer training, treatment rooms, workrooms and an armory.
 
Client/Owner: General Services Administration (GSA)
Design-Build Team
Design-Builder Hensel Phelps 
General Contractor Hensel Phelps
Architects Gensler (Architect of Record)
Krueck + Sexton (Lead Designer - Bridging Architect/Engineer)
Engineers Syska Hennessy Group, Inc. (MEP & Fire Protection Engineer)
Walter P Moore (Structural Engineer)
Rolf Jensen & Associates
Atkins
Specialty Contractors M.C. Dean, Inc. (Electrical Subcontractor)
John J. Kirlin, Inc.
Enclos Corp.
Specialty Consultants Gordon H. Smith Corporation
Hinman Consulting Engineers, Inc.
 
Duration of Construction: 25 months
Actual Project Cost: $157,200,728