Maya Angelou Learning Center

Maya Angelou Learning Center
Washignton, D.C.
Challenge Design-Build Project Delivery Addressed:
The owner chose design-build project delivery to mitigate anticipated phasing, occupational and site utilization challenges by engaging the general contractor early in the process.
 
Summary:
The See Forever Foundation creates learning communities in under-served urban areas where all students, particularly those who have not succeeded in traditional schools, can strive for academic excellence. Forrester Construction managed the design phase, provided value engineering services and renovated an existing facility to create the Maya Angelou Learning Center. This multi-phased project involved modernizing 115,000-square-foot in the existing Bruce Evans School. Originally constructed in the early 1960s, the building was formerly a District of Columbia Public School which is now being leased from the city by the See Forever Foundation. The completed project houses Maya Angelou Learning Center’s high school program and their Young Adult Learning Center. This LEED Certified facility features new and remodeled classrooms, upgraded science labs, multiple computer labs, a flexible workshop, an improved library, administrative and counselors' offices, a health suite, a renovated cafeteria and improved common areas.
 
Client/Owner: See Forever Foundation Maya Angelou Public Charter Schools
Design-Build Team
Design-Builder Forrester Construction Company
General Contractor Forrester Construction Company
Architect Studio 27 Architecture
Engineers Ehlert Bryan
Christopher Consultants, Ltd.
Other Key Professionas Metropolitan Consulting Engineers
Jair Lynch Company
Forrester Construction Company
See Forever Foundation
 
Duration of Construction: 12 months
Actual Project Cost: Phase 1 $4,720,531 , Phase 2 $6,810,899