P-822 MCAS Terminal Operations & AFRS Complex


 

Kaneohe, Hawaii


Challenge Design-Build Project Delivery Addressed:
NAVFAC continues to be pressured to do more with less. Use of the design-build process saves significant time/costs and promotes innovation and improved quality.
 
Summary:
dck-ecc pacific guam, LLC (dck-ecc) designed and constructed the $47 million LEED Silver P-822 Marine Corps Air Station (MCAS) Operations Complex project on Marine Corps Base Hawaii (MCBH), Kaneohe, Hawaii. The project scope included the design-build of a Terminal Operations Complex, an Airfreight Cargo Facility, an Aircraft Fire and Rescue Station (AFRS), a mechanical plant and Aircraft Parking Apron. The Terminal Operations Complex is a two-story 30,700-square-foot building that houses all terminal operations activities and support offices. The cargo facility is comprised of palletizing and conveyance equipment. The AFRS is a state-of-the-art 17,100-square-foot multi-story airfield firefighting facility that includes five apparatus bays; administrative offices; storage and support areas; training, exercise and residential areas; an elevated 360°dispatch tower; access driveways; and parking.
Client/Owner: NAVFAC
Design-Build Team
Design-Builder dck-ecc pacific guam, LLC
General Contractor Not applicable to this project
Architects RIM Architects
CDS International (Site Architect)
Engineers Baldridge & Associates Structural Engineering
Atkins (Airfield Engineer/Site Electrical Engineer)
Specialty Contractors Alakai Mechanical Corporation
Aloha Fire Systems
Grace Pacific
Group Builders
Jayar Construction
PC Enterprises
Porges Electrical Group
RM Nakamura Plumbing
South Pacific Steel
Swanson Steel Erectors, Inc.
Specialty Consultants: Masa Fujioka and Associates; Popov; Hayre McElroy; Elevations Inc. 
Other Key Professionals SS Dannaway and Associates
Wayne Wixon and Associates
Sam Hirota and Associates
PC Enterprises
Atkins
Miyabara  Associates
Censeo + AV Acoustics LLC
Geolabs Inc.
Kennedy/Jenks Consultants
K Design Group
Pacific Studio
William Caruso and Associates
 
Duration of Construction: 32 months
Actual Project Cost: $47,065,414