Lenovo - Project Oasis

Lenovo - Project Oasis

Challenge Design-Build Project Delivery Addressed:
Design-Build was literally the only way this project could have been accomplished given the timeline requirements. Design-Build of 465,000 SF of existing office space into a mixture of class-A office space and electronics labs inclusive of all new Mechanical and Electrical systems, structural upgrades and high-end finishes throughout the space. To program, design and build a renovation of this magnitude in just 6 months, Design-Build Delivery facilitated a target value delivery through real-time designer / end-user programming and prototyping, continuous estimating and fast-track scheduling. Without this collaborative approach, trust and respect, the project could not have been accomplished on time.

Summary:
Design-build delivery coupled with collaboration was the formula to overcome an impossible timeline to design and build Lenovo’s campus for their to-be acquired IBM x-86 server division. 465,000 SF of major renovation, 2 four-story buildings, in 6 short months. 107 days from building permit to TCO, at a pace of nearly $1M per day, this project exemplifies implementations of lean techniques, sustainable design / construction and most importantly teamwork, overcoming a nearly impossible schedule successfully.
 
Design-Build Team
Client/Owner Lenovo.com
Design-Builder The Whiting-Turner Contracting Company
General Contractor The Whiting-Turner Contracting Company
Architects IDC Architects, Perkins + Will
Engineers Stroud, Pence & Associates, LTD, CH2M
Specialty Contractor Inertech
Specialty Consultant Thorburn Associates, Inc.
Duration of Construction: 6 months
Project Cost: (not available)