Skip Navigation LinksHome > Awards > 2017 Project/Team Awards > Los Angeles Unified School District - Jordan High School Redevelopment Project
  • LinkedIn
  • Google
  • Delicious
  • Digg
  • Add to Favorites


Los Angeles Unified School District - Jordan High School Redevelopment Project

Los Angeles Unified School District - Jordan High School Redevelopment Project
Challenge Design-Build Project Delivery Addressed:
LAUSD’s chose to use design-build to mitigate a number of challenges, including; Speed of Delivery, Cost Control, Quality and Team Integration. Ultimately they were looking to reduce comparable project costs, expedite the project’s completion and control project costs through integration, collaboration and innovative design and construction solutions.

Summary:
The Jordan High School Project’s transformed the campus from a sea of asphalt, portables and wire-topped fencing, into a point of pride for the students that enhanced learning and the community. Creating two learning academies ultimately improved the educational model on campus and increased graduation rates significantly. We achieved these goals by collaborating with District stakeholders, the community, students and staff creating an outstanding learning environment and a campus that focused on the community first.
 
Design-Build Team
Client/Owner Los Angeles Unified School District
Design-Builder Swinerton Builders
General Contractor Swinerton Builders
Architect DLR Group
Engineers Budlong & Associates, Inc., Saiful Bouqet Structural Engineers
Specialty Consultant AHBE Landscape Architects
Duration of Construction: 38 months
Project Cost: $72,682,845